Sterlite Power secures ₹1,373 cr funding from PFC transmission project
30 May 2024
Funding Achievement and Trust:
Secured ₹1,373 crore from Power Finance Corporation for the NKTL project, reflecting PFC's confidence in Sterlite Power's expertise.
Project Components:
Includes a 6000 MVA, 765/400kV substation at Neemrana and a 400 kV transmission line network spanning 250 km.
Infrastructure Connectivity:
Links Neemrana substation with Kotputli, Gurgaon, and Sohna substations, enhancing grid stability.
Acquisition and Operational Framework:
Acquired in November 2023 and executed on a 35-year Build, Own, Operate, and Transfer (BOOT) basis.
Sterlite Electric
-8.97%
Publisher:The Hindu Business line