Sterlite Power wins the Khavda Phase-IV project to evacuate 7 GW from Gujarat’s 30 GW renewable park, advancing India's 500 GW target.
Sterlite Power wins the Khavda Phase-IV project to evacuate 7 GW from Gujarat’s 30 GW renewable park, advancing India's 500 GW target.
Sterlite Electric
-8.97%
Expert Analysis
Sterlite Power Wins Second Green Energy Project in Gujarat.
Expert Analysis:
Project Acquisition: Sterlite Power Transmission Secures Khavda Phase-IV (7GW): Part C project for developing a transmission system.
Renewable Energy Park: The project aims to evacuate power from Gujarat’s 30 GW hybrid (solar and wind) renewable energy park at Khavda, inaugurated by the Hon’ble Prime Minister of India in December 2020.
Company Milestones: This is Sterlite Power’s second green energy transmission project in Gujarat and its fifth overall.
Alignment with National Goals: The project aligns with India's goal of installing 500 GW of renewable energy capacity by 2030.